The current TIP includes projects from Fiscal Year 2024 to 2027.

The fiscal year begins every year on July 1st and ends June 30. For example, the 2024 Fiscal Year began in July of 2023. Project funding abbreviations are defined here

IR 76 | Akron
PID# 100713
$144,483,188— Total Project Cost
Improvements to increase capacity and improve safety including structural rehabilitation and noise walls on the kenmore leg
PID# 100713
$144,483,188— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
P
FED
$1,231,830
2025
P
STATE
$136,870
2025
R
FED
$415,000
2025
R
STATE
$150,735
2025
County: Summit
More Info
SR 21 | Chippewa Twp
PID# 101439
$40,796,386— Total Project Cost
Resurfacing, bridge maintenance, drainage & culvert replacement, and safety improvements at clinton rd, edwards rd, and grill rd from summit county line to north of wayne county line
PID# 101439
$40,796,386— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
P
FED
$1,872,000
2024
P
STATE
$468,000
2024
P
SAFETY-F
$208,000
2024
P
SAFETY-S
$52,000
2024
C
FED
$26,788,331
2024
C
STATE
$6,713,138
2024
C
SAFETY-F
$3,316,180
2024
C
SAFETY-S
$345,785
2024
C
FED
$400,000
2025
C
STATE
$100,000
2025
County: Wayne
More Info
IR 76/IR 77/SR 8 | Akron
PID# 102329
$169,097,164— Total Project Cost
Resurfacing on IR 76 and IR 77, reconstruct left exit ramps at the central interchange 
PID# 102329
$169,097,164— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
GARVEE
$7,285,182
2024
O
GARVEE
$6,058,791
2025
O
GARVEE
$6,058,791
2026
O
GARVEE
$6,058,791
2027
County: Summit
More Info
SR 91 | Stow
PID# 102745
$12,393,070— Total Project Cost
Reconstruction, curb ramps, sidewalks, storm sewer, and signals from south corp limit to south of norton ave
PID# 102745
$12,393,070— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
R
TASA
$56,000
2024
R
LOCAL
$14,000
2024
C
STBG
$4,660,000
2025
C
CMAQ
$1,197,690
2025
C
TASA
$617,818
2025
C
FED
$1,496,790
2025
C
STATE
$99,510
2025
C
LOCAL
$4,251,263
2025
County: Summit
More Info
Freedom Trail Middlebury Connector | Tallmadge/Stow/Kent
PID# 102796
$3,418,103— Total Project Cost
Construct multi-use trail from portage hike and bike to freedom trail
PID# 102796
$3,418,103— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
TASA
$700,000
2024
C
LOCAL
$1,465,973
2024
County: Summit
More Info
SR 14/SR 43 Intersection, SR 14/SR 303/Ranch Rd Intersection | Streetsboro
PID# 105213
$5,846,200— Total Project Cost
Resurfacing and reconstruction of sr 14/sr 43 intersection, new signal, remove westbound slip ramp of sr 14/sr 303/ ranch rd intersection
PID# 105213
$5,846,200— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$1,089,752
2026
C
CMAQ
$459,517
2026
C
FED
$2,030,400
2026
C
LOCAL
$2,266,531
2026
County: Portage
More Info
Ravenna Rd Bridge | Franklin Twp
PID# 105556
$2,526,099— Total Project Cost
Replace bridge and add lanes for portage hike and bike trail
PID# 105556
$2,526,099— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
TASA
$313,600
2025
C
FED
$1,167,200
2025
C
LOCAL
$821,200
2025
County: Portage
More Info
Freedom Trail Phase 4 | Akron
PID# 107930
$5,108,940— Total Project Cost
Construct multi-use trail from mill st to rosa parks blvd
PID# 107930
$5,108,940— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
TASA
$700,000
2025
C
LOCAL
$2,757,918
2025
C
BR
$1,265,164
2025
C
OTC
$237,218
2025
County: Summit
More Info
Wooster Rd West | Barberton
PID# 108240
$11,471,016— Total Project Cost
Resurfacing and reconstruction with possible road diet from 31st st to hudson run rd, hudson run rd to 2nd st nw
PID# 108240
$11,471,016— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$6,000,000
2024
C
SAFETY-F
$1,171,559
2024
C
SAFETY-S
$130,173
2024
C
LOCAL
$2,879,712
2024
County: Summit
More Info
SR 59 | Cuyahoga Falls/Silver Lake/Stow
PID# 110743
$3,014,100— Total Project Cost
Resurfacing from sr 8 to portage county line
PID# 110743
$3,014,100— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
FED
$2,273,680
2024
C
STBG
$150,000
2024
C
STATE
$73,720
2024
C
LOCAL
$492,700
2024
County: Summit
More Info
IR 77 | Bath Twp
PID# 111404
$60,329,533— Total Project Cost
Widen to 6 lanes from ghent rd to everett rd
PID# 111404
$60,329,533— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
FED
$49,255,820
2025
C
STATE
$7,514,280
2025
County: Summit
More Info
IR 77 | Bath Twp
PID# 111405
$76,658,059— Total Project Cost
Widen to 6 lanes from ghent rd to everett rd
PID# 111405
$76,658,059— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
FED
$61,787,542
2024
C
STATE
$9,008,649
2024
County: Summit
More Info
Air Quality | Summit/Portage/Wayne
PID# 111429
$100,000— Total Project Cost
Promotion of activities to improve air quality such as biking and walking
PID# 111429
$100,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
CMAQ
$100,000
2024
County: Summit/Portage/Wayne
More Info
Rideshare | Summit/Portage/Wayne
PID# 111433
$80,000— Total Project Cost
Promotion of carpooling
PID# 111433
$80,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
CMAQ
$80,000
2024
County: Summit/Portage/Wayne
More Info
SR 59 | Kent
PID# 112026
$28,559,046— Total Project Cost
Reconstruct to include raised medians, bus pull-offs, new sewers, two roundabouts, upgrade lighting, and replace sidewalks from willow st to horning rd
PID# 112026
$28,559,046— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
CMAQ
$5,661,065
2025
C
TASA
$700,000
2025
C
FED
$500,000
2025
C
STATE
$500,000
2025
C
SAFETY-F
$1,142,268
2025
C
SAFETY-S
$1,232,879
2025
C
LOCAL
$5,446,308
2025
C
CRP
$4,140,000
2025
C
RAISE
$5,141,694
2025
County: Portage
More Info
SR 261 | Akron
PID# 112716
$15,364,179— Total Project Cost
Corridor improvements from olive st to riverside dr
PID# 112716
$15,364,179— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
CMAQ
$900,000
2025
C
STBG
$6,000,000
2025
C
SAFETY-F
$3,500,000
2025
C
LOCAL
$4,964,179
2025
County: Summit
More Info
Hopocan/Norton/Snyder | Barberton
PID# 112735
$2,785,889— Total Project Cost
Resurfacing hopocan ave from hilldale ave to 8th st, norton ave from 17th st nw to barber rd, snyder ave from 2nd st sw to 5th st se
PID# 112735
$2,785,889— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$1,602,334
2024
C
LOCAL
$1,169,755
2024
County: Summit
More Info
Cleveland Massillon Sidewalks | Bath Twp
PID# 112788
$744,467— Total Project Cost
Sidewalk on west side of roadway from sr 18 to springside dr
PID# 112788
$744,467— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
P
TASA
$20,804
2024
P
LOCAL
$5,201
2024
R
TASA
$60,000
2024
R
LOCAL
$15,000
2024
C
TASA
$375,732
2025
C
LOCAL
$188,400
2025
County: Summit
More Info
Stow Bike & Hike Trail | Stow/Silver Lake/Cuyahoga Falls
PID# 113016
$1,017,600— Total Project Cost
Construct multi-use trail from sr 8 pedestrian bridge to springdale rd
PID# 113016
$1,017,600— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
TASA
$700,000
2027
C
LOCAL
$280,000
2027
County: Summit
More Info
Highland/Valley View Rd | Macedonia
PID# 113161
$3,347,859— Total Project Cost
Intersection improvements at highland and valley view rd intersection
PID# 113161
$3,347,859— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
R
CMAQ
$105,680
2024
R
LOCAL
$26,420
2024
C
CMAQ
$1,703,131
2025
C
STBG
$302,051
2025
C
LOCAL
$1,210,577
2025
County: Summit
More Info
Ravenna/Shepard/Broadway | Macedonia/Twinsburg
PID# 113165
$3,513,020— Total Project Cost
Add right turn lanes on ravenna rd, add left turn lane on shepard, sidewalks and signal improvements at intersection
PID# 113165
$3,513,020— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
R
CMAQ
$116,996
2024
R
LOCAL
$29,249
2024
C
CMAQ
$1,252,292
2025
C
CMAQ
$1,369,288
2025
C
LOCAL
$655,394
2025
County: Summit
More Info
Ravenna Rd | Twinsburg/Hudson
PID# 113175
$1,283,915— Total Project Cost
Resurfacing from old mill rd to portage county line
PID# 113175
$1,283,915— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$600,000
2025
C
LOCAL
$670,415
2025
County: Summit
More Info
IR 77/SR 8 | Akron
PID# 114865
$75,000,000— Total Project Cost
Corridor improvements on mainline, service roads and ramps from just north of lovers lane to sr 8 and sr 8 from I-77 to just north of perkins st.
PID# 114865
$75,000,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
P
FED
$1,600,000
2025
P
STATE
$400,000
2025
R
FED
$800,000
2025
R
STATE
$200,000
2025
County: Summit
More Info
Canton Rd | Springfield Twp
PID# 115358
$971,584— Total Project Cost
Resurfacing from pontius rd to tisen rd
PID# 115358
$971,584— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$528,000
2024
C
LOCAL
$443,584
2024
County: Summit
More Info
Old Forge Rd | Brimfield Twp
PID# 115359
$799,953— Total Project Cost
Resurfacing from sunnybrook rd to ranfield rd
PID# 115359
$799,953— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$628,362
2027
C
LOCAL
$157,091
2027
County: Portage
More Info
N Chestnut St/S Prospect St | Ravenna
PID# 115360
$905,000— Total Project Cost
Resurfacing chestnut st from sr 59 main st to sr 14, resurfacing s prospect st from the south corp line to sr 59
PID# 115360
$905,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$751,500
2024
C
LOCAL
$153,500
2024
County: Portage
More Info
Springside Dr | Bath Twp
PID# 116457
$1,047,654— Total Project Cost
Install new sidewalk from sr 18 to cleveland massillon rd
PID# 116457
$1,047,654— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
P
TASA
$35,518
2024
P
LOCAL
$8,879
2024
R
LOCAL
$28,059
2024
C
TASA
$600,000
2027
C
LOCAL
$292,095
2027
County: Summit
More Info
Rubber City Heritage Trail Ph 2 | Akron
PID# 116464
$954,500— Total Project Cost
Construct multi-use trail from huntington ave to s arlington st
PID# 116464
$954,500— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
TASA
$700,000
2025
C
LOCAL
$223,000
2025
County: Summit
More Info
Frost Rd Phase 2 | Streetsboro
PID# 116470
$626,312— Total Project Cost
Resurfacing East of Sr 43 to Page Rd
PID# 116470
$626,312— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
FED
$8,168
2024
C
STBG
$522,942
2024
C
LOCAL
$95,202
2024
County: Portage
More Info
Highland Rd | Twinsburg
PID# 116479
$608,840— Total Project Cost
Resurfacing from hadden rd to darrow rd
PID# 116479
$608,840— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
STBG
$522,000
2024
LOCAL
$86,840
2024
County: Summit
More Info
Glenwood Dr | Twinsburg
PID# 116505
$977,400— Total Project Cost
Resurfacing from ravenna rd to darrow rd
PID# 116505
$977,400— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$787,500
2027
C
LOCAL
$189,900
2027
County: Summit
More Info
Miller Rd | Akron/Fairlawn
PID# 116539
$544,100— Total Project Cost
Resurfacing from ridgewood rd to w market st 
PID# 116539
$544,100— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$409,500
2024
C
LOCAL
$134,600
2024
County: Summit
More Info
Albrecht Ave | Springfield Twp/Mogadore
PID# 116556
$2,003,463— Total Project Cost
Resurfacing from stull ave to cleveland ave
PID# 116556
$2,003,463— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$787,500
2027
C
LOCAL
$1,215,963
2027
County: Summit
More Info
S Main St | Coventry Twp
PID# 116557
$1,663,629— Total Project Cost
Resurfacing from green north corp limit to warner rd
PID# 116557
$1,663,629— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$787,500
2027
C
LOCAL
$855,629
2027
County: Summit
More Info
Greenwich Rd | Norton
PID# 116620
$1,259,840— Total Project Cost
Resurfacing from s medina line rd to cleveland massillon rd
PID# 116620
$1,259,840— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$787,500
2027
C
LOCAL
$472,339
2027
County: Summit
More Info
Graham Rd | Stow
PID# 116623
$994,175— Total Project Cost
Resurfacing east of sr 91 to newcomer rd
PID# 116623
$994,175— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$787,500
2027
C
LOCAL
$190,575
2027
County: Summit
More Info
Valley View Rd | Sagamore Hills Twp
PID# 116703
$1,522,225— Total Project Cost
Resurfacing from dunham rd to olde eight rd
PID# 116703
$1,522,225— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$787,500
2027
C
LOCAL
$734,725
2027
County: Summit
More Info
Bailey Rd | Cuyahoga Falls
PID# 116740
$890,800— Total Project Cost
Resurfacing front st to graham rd
PID# 116740
$890,800— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$700,000
2027
C
LOCAL
$175,000
2027
County: Summit
More Info
Hudson Dr | Cuyahoga Falls
PID# 116741
$1,026,531— Total Project Cost
Resurfacing from front st to graham rd
PID# 116741
$1,026,531— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$700,000
2027
C
LOCAL
$310,831
2027
County: Summit
More Info
Wyoga Lake Rd | Cuyahoga Falls
PID# 116742
$7,736,000— Total Project Cost
Add two way left turn lane, add right turn lanes where warranted, add a new signal at walsh hs main entrance from steels corners rd to seasons rd
PID# 116742
$7,736,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
R
STBG
$461,000
2025
R
LOCAL
$115,250
2025
C
STBG
$5,639,000
2026
C
LOCAL
$1,284,750
2026
County: Summit
More Info
Heartland Trail Ph 4a | Chippewa Twp
PID# 116841
$819,703— Total Project Cost
Construct multi-use trail from north of market st to coal bank rd 
PID# 116841
$819,703— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
P
TASA
$14,071
2025
P
LOCAL
$3,518
2025
C
TASA
$590,583
2026
C
LOCAL
$147,646
2026
County: Wayne
More Info
Veterans Rails to Trails | Hudson
PID# 116868
$2,382,800— Total Project Cost
Construct multi-use trail from springdale rd to barlow rd
PID# 116868
$2,382,800— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
TASA
$700,000
2027
C
LOCAL
$1,600,000
2027
County: Summit
More Info
S Arlington Rd | Green
PID# 116917
$21,922,841— Total Project Cost
Widen to four lanes, new roundabouts at boettler rd and southwood dr, new sidewalks from south of boettler rd to north of september dr
PID# 116917
$21,922,841— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
R
CMAQ
$762,124
2025
R
STBG
$674,602
2025
R
LOCAL
$359,182
2025
C
CMAQ
$3,305,666
2026
C
STBG
$1,699,040
2026
C
LOCAL
$7,622,227
2026
C
CRP
$2,000,000
2026
C
SAFETY-F
$3,500,000
2026
C
FED
$2,000,000
2026
County: Summit
More Info
Hudson Signals | Hudson
PID# 116924
$3,339,470— Total Project Cost
Upgrade 14 signals to adaptive “smart” signals on sr 91 and sr 303
PID# 116924
$3,339,470— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
CMAQ
$2,664,480
2024
C
LOCAL
$674,990
2024
County: Summit
More Info
Barlow Rd | Hudson
PID# 116925
$497,504— Total Project Cost
Resurfacing from norfolk southern railroad to stow rd
PID# 116925
$497,504— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$439,744
2027
C
LOCAL
$48,860
2027
County: Summit
More Info
SR 91/Terex Rd Intersection | Hudson
PID# 116929
$570,002— Total Project Cost
Intersection improvements to improve left turn offsets, extend eastbound left turn lane and add new westbound turn lane into joann fabrics entrance
PID# 116929
$570,002— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$400,142
2026
C
LOCAL
$154,960
2026
County: Summit
More Info
Valley View Rd | Hudson
PID# 116932
$974,170— Total Project Cost
Resurfacing from hudson north corp limit to sr 91 
PID# 116932
$974,170— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$787,500
2024
C
LOCAL
$169,970
2024
County: Summit
More Info
Cleveland/Diagonal/Ravenna | Ravenna/Franklin Twp
PID# 116939
$1,173,158— Total Project Cost
Resurfacing cleveland rd from ravenna north corp limit to sr 14, resurfacing ravenna rd from brady lake rd to sr 43, resurfacing diagonal rd from sr 43 to ravenna rd 
PID# 116939
$1,173,158— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$935,966
2027
C
LOCAL
$215,992
2027
County: Portage
More Info
SR 59 Signals | Stow
PID# 116990
$1,953,281— Total Project Cost
Signal upgrades from sycamore dr to fishcreek rd
PID# 116990
$1,953,281— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
CMAQ
$1,520,145
2025
C
LOCAL
$380,036
2025
County: Summit
More Info
S Main St | Green
PID# 117105County
$1,481,939— Total Project Cost
Resurfacing south of west caston rd to sr 619
PID# 117105County
$1,481,939— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$787,500
2024
C
LOCAL
$694,439
2024
County: Summit
More Info
Cleveland Massillon Rd Ph 3 | New Franklin
PID# 117138
$993,236— Total Project Cost
Resurfacing from serfass rd to grill rd 
PID# 117138
$993,236— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$700,000
2027
C
LOCAL
$275,336
2027
County: Summit
More Info
Air Quality | Summit/Portage/Wayne
PID# 118654
$100,000— Total Project Cost
Promotion of activities to improve air quality such as biking and walking 
PID# 118654
$100,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
CMAQ
$100,000
2025
County: Summit/Portage/Wayne
More Info
Air Quality | Summit/Portage/Wayne
PID# 118655
$100,000— Total Project Cost
Promotion of activities to improve air quality such as biking and walking 
PID# 118655
$100,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
CMAQ
$100,000
2026
County: Summit/Portage/Wayne
More Info
Air Quality | Summit/Portage/Wayne
PID# 118656
$400,000— Total Project Cost
Promotion of activities to improve air quality such as biking and walking 
PID# 118656
$400,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
CMAQ
$100,000
2027
County: Summit/Portage/Wayne
More Info
Rideshare | Summit/Portage/Wayne
PID# 118657
$80,000— Total Project Cost
Promotion of Carpooling 
PID# 118657
$80,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
CMAQ
$80,000
2025
County: Summit/Portage/Wayne
More Info
Rideshare | Summit/Portage/Wayne
PID# 118658
$80,000— Total Project Cost
Promotion of Carpooling 
PID# 118658
$80,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
CMAQ
$80,000
2026
County: Summit/Portage/Wayne
More Info
Rideshare | Summit/Portage/Wayne
PID# 118659
$80,000— Total Project Cost
Promotion of Carpooling 
PID# 118659
$80,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
CMAQ
$80,000
2027
County: Summit/Portage/Wayne
More Info
SR 8 | Stow/Hudson
PID# 76721
$67,725,190— Total Project Cost
Reconstruction from graham rd to north of sr 303 
PID# 76721
$67,725,190— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
GARVEE
$4,764,213
2024
O
GARVEE
$4,764,214
2025
O
GARVEE
$4,764,214
2026
O
GARVEE
$4,764,214
2027
County: Summit
More Info
IR 76 | Norton/Barberton
PID# 93501
$89,048,328— Total Project Cost
Resurfacing from medina county line to sr 21, widening to 6 lanes from sr 21 to central ave 
PID# 93501
$89,048,328— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
GARVEE
$9,082,587
2024
O
GARVEE
$8,918,038
2025
O
GARVEE
$8,075,717
2026
O
GARVEE
$2,285,755
2027
County: Summit
More Info
IR 76 | Barberton/Akron
PID# 96670
$37,585,338— Total Project Cost
Widen to 6 lanes and reconfigure wooster rd /east ave/state st interchanges from central ave to 27th st 
PID# 96670
$37,585,338— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
O
GARVEE
$2,280,740
2024
O
GARVEE
$2,280,741
2025
O
GARVEE
$2,280,740
2026
O
GARVEE
$2,280,740
2027
County: Summit
More Info
EAST AVE | TALLMADGE
PID# 112869
$14,218,294— Total Project Cost
Add two-way left turn lane, curbs, and sidewalks from community rd to portage county line
PID# 112869
$14,218,294— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
R
SAFETY-F
$734,615
2025
R
SAFETY-S
$81,624
2025
County: SUMMIT
More Info
DOYLESTOWN RD | MILTON/CHIPPEWA TWPS
PID# 116855
$636,036— Total Project Cost
Resurfacing from doylsetown-rittman east corp limit to doylestown west corp limit; portage-whitman rd to doylestown west corp limit
PID# 116855
$636,036— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
STBG
$508,829
2027
C
LOCAL
$127,207
2027
County: WAYNE
More Info
HIGHLAND RD | MACEDONIA
PID# 121067
$2,950,600— Total Project Cost
New signals at sr 8 and s bedford rd; new wb left turn lane at sr 8; new sb right turn lane at s bedford rd; new sidewalk along s bedford rd
PID# 121067
$2,950,600— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
R
CMAQ
$213,600
2027
R
LOCAL
$53,400
2027
County: SUMMIT
More Info
KILLIAN RD/PICKLE RD ROUNDABOUT | SPRINGFIELD TWP
PID# 121287
$2,640,600— Total Project Cost
Roundabout at killian/pickle rd intersection; reprofiling the eastern approach; sidewalks
PID# 121287
$2,640,600— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
R
CRP
$240,000
2027
R
LOCAL
$60,000
2027
County: SUMMIT
More Info
NORTH MANTUA ST IMPROVEMENTS | KENT
PID# 121376
$6,025,000— Total Project Cost
Pavement reconstruction/resurfacing, signal upgrade at roosevelt hs, new sidewalks, lighting, curb ramps, storm sewers, signing, and pavement markings from needham ave to north of davey tree entrance
PID# 121376
$6,025,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
CRP
$2,000,000
2027
C
LOCAL
$3,800,000
2027
C
STATE
$225,000
2027
County: PORTAGE
More Info
GRAHAM RD SIGNALS | STOW
PID# 121457
$3,575,000— Total Project Cost
Replace/update 9 signals (poles, mast arms, controllers, signal heads, signs, preemption, and ped signals) along the graham rd corridor from bailey rd to newcomer rd
PID# 121457
$3,575,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
C
CMAQ
$2,860,000
2027
C
LOCAL
$715,000
2027
County: SUMMIT
More Info
N MAIN ST HIGH LEVEL BRIDGE | AKRON
PID# 115383
$10,408,507— Total Project Cost
Replace bridge over the cuyahoga river
PID# 115383
$10,408,507— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
P
BR
$4,210,526
2025
P
OTC
$789,474
2025
P
LOCAL
$1,292,228
2025
P
FED
$4,116,279
2025
County: SUMMIT
More Info
SR 59 ALT TRANSPORTATION | KENT/FRANKLIN TWP
PID# 118500
$7,438,234— Total Project Cost
Reducing lane widths, extending and adding sidewalks, curb ramps, mid-block crossings, ada bus stops and shelters, upgrade ped signals from east of horning rd to sr 261
PID# 118500
$7,438,234— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
P
SAFETY-F
$547,695
2024
P
LOCAL
$60,855
2024
P
SAFETY-F
$79,816
2026
P
LOCAL
$8,868
2026
C
STBG
$3,212,000
2027
C
LOCAL
$3,529,000
2027
County: PORTAGE
More Info
RUBBER CITY HERITAGE TRAIL PH 3 | AKRON
PID# 121747
$2,015,000— Total Project Cost
New multi-modal trail along abandoned railroad from e exchange st/huntington ave intersection to brown st/johnston st intersection
PID# 121747
$2,015,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
P
TASA
$133,600
2025
P
LOCAL
$33,400
2025
County: SUMMIT
More Info
STOW/SUMMIT PED IMPROVEMENTS | KENT
PID# 121755
$2,348,745— Total Project Cost
Replace bridge over cuyahoga river
PID# 121755
$2,348,745— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
P
TASA
$200,000
2026
P
BR
$42,756
2026
P
LOCAL
$60,689
2026
County: PORTAGE
More Info
State Rd Widening | Cuyahoga Falls
PID# 121863
$15,000,000— Total Project Cost
Pavement replacement, adding two-way left turn lane, roundabout at Quick Rd, adding sidewalk on north/west side from Quick Rd to Wyoga Lake Rd
PID# 121863
$15,000,000— Total Project Cost
Project Funding Details
Phase:Fund Type:Amount:Year:
R
STBG
$69,520
2027
R
LOCAL
$17,380
2027
County: Summit
More Info